CHAPTER 7
CONTRACT ADMINISTRATION, ENFORCEMENT
AND LEGAL REMEDIES

OVERVIEW
The procurement process does not end with the award of contract. The contractor’s performance must be appropriately monitored, the contract itself may be amended in response to unforeseen problems and the contract must be eventually closed-out or terminated, if not renewed. In performing these tasks, the department shall:

  • Assure a mutual understanding of the rights, obligations and responsibilities of both the contractor and the department under the contractual agreement;
  • Initiate any contract changes desired by the department;
  • Protect the City’s interests in the event of default by the contractor or contract termination; and
  • Evaluate the performance of the contractor for future use by other City departments.

CONTRACT MONITORING
Contract monitoring allows the department to diagnose problems that may lead to work change orders, schedule slippages, cost overruns or unacceptable product quality. Four steps shall be taken to guard against these problems: (1) designate a Contract Administrator (in some instances this may be Purchasing); (2) establish administrative controls; (3) monitor work progress regularly; and (4) establish cost controls (these may have already been established as a part of the bid specification).

It has been demonstrated that the City receives the greatest benefit from certain contracts when the engagement is considered a joint undertaking and City personnel are active participants.

This provides the employees with useful training opportunities and valuable knowledge of what the contractor has done, why it was done, and how the agency can benefit by it. This often represents knowledge that could never be derived simply through the analysis of the end product. City personnel, working with the contractor, can give the project continuity at the operating level in subsequent months. Also, these individuals can lend "in-house acceptance" to the project and broaden its chances for an enduring success.

CONTRACT ADMINISTRATOR
One person shall be given the responsibility for administering the contract. This individual (Contract Administrator) shall be the single contact person and shall be responsible for the following actions:

  • Coordinating the flow of information between the contractor and the department.
  • Responding to requests made by the contractor.
  • Monitoring disbursements against the contractual budget.
  • Monitoring the procurement progress against the work scheduled.
  • Coordinating the delivery of data or services to the contractor.
  • Approving all contract deliverables.

The Contract Administrator shall have a technical background to promptly diagnose problems in the development, testing, implementation and operation of the product or service.

The department head or his designee shall formally designate the Contract Administrator by name and clearly define his or her responsibilities. If not designated in the contract, this designation shall be sent, by letter, to the contractor and user department.

Administrative Controls
The Contract Administrator and the contractor’s project manager shall review the rights, obligations and responsibilities of both parties soon after the contract is signed. During this review, they shall again discuss all issues that were difficult to settle during negotiations since these issues are the most likely points for future disagreement. They shall review the following items:

  • Communication channels between the department and the contractor, designating specific personnel by name, title, responsibility, address and telephone number.
  • Major milestones, including the due dates for all contract deliverables and the provision of all property, material and manpower by the jurisdiction to the contractor.
  • Administrative and technical requirements for reporting work progress.
  • Administrative requirements for reporting expenses and procedures for progress payments or other financial arrangements.
  • Administrative and technical procedures for inspecting and accepting contract deliverables.
  • Administrative procedures for authorizing modifications to the contract.

Work Progress
Written progress reports are essential if the Contract Administrator is to maintain control over the project and shall be required in the contract. Regular progress reports shall describe actual progress during the current reporting period, deviations from planned progress and problems anticipated in the next reporting period. Information shall be maintained and accumulated for future use. Progress reports shall also explain any reasons for these deviations (current and expected); outline what is being done to correct them; and indicate what assistance, if any, is required from the department.

Control is facilitated by requiring the contractor to submit: (1) a schedule for approval by the Contract Administrator and (2) a comparison of actual progress to the schedule with each written progress report.

Cost Controls
Cost controls are another means of determining whether the procurement is proceeding as planned. Cost controls warn the Contract Administrator of any problems the contractor may have in completing the required work within the contractual cost limits by showing the relationships between actual and expected costs. Cost controls are also used with cost-reimbursement contracts as a means of noting deviation from target costs. The Contract Administrator can then suggest actions that will reduce those and future deviations, thereby keeping actual costs as low as possible.

Cost control is maintained by requiring the contractor to submit: (1) a cost plan for approval by the Contract Administrator and (2) a cost status report with each written progress report.

A cost plan is a task-by-task budget of direct labor costs, fringe benefits, overhead, direct materials, direct services, other expenses, as well as general and administrative costs. The requirement for a cost plan will depend on the size and complexity of the contract. If the department feels a cost plan is required, that requirement and related conditions shall be specified in the contract.

A cost status report shall provide information using the same cost elements found in the cost plan and for updating the department on actual costs, cumulative cost-to-date and variances between actual and planned cost-to-date.

The following are examples of cost control criteria:

  • Estimated costs at completion - the latest estimate and original planning estimate.
  • Variances between estimated and planned costs at completion.
  • Explanations of the nature of any variances between actual and planned costs-to-date or estimated and planned costs at completion.
  • Descriptions of the actions proposed or taken to avoid or minimize any impending cost overruns
  • Ensuring the timely submittal of all progress and cost status reports.
  • Comparing these reports with the schedule and cost plans.
  • Ensuring that the contractor receives the governmental support promised him in a timely fashion.
  • Ensuring the timely delivery of all products, services and documentation required of the County by the contract.
  • Ensuring the timely performance of tasks required of the City.
  • Ensuring that all quality control procedures (i.e., tests and inspections) are followed by the appropriate requirements and technical support specialists immediately after the receipt of each contract deliverable.
  • Reviewing the results of tests and inspections before closing out the contract.
  • Coordinating all other contractual controls.

 

AMENDING THE CONTRACT
Unforeseen problems, circumstances and events may make a contract amendment a necessity. To protect the City’s interests, the Contract Administrator or department head shall supervise all discussion with the contractor regarding amendments, but only after doing so with the Purchasing Agent. All amendments must be in writing and signed in the same manner
as the original contract. The dollar amount of the amended contract must not exceed the signatory’s limitations.

For purposes of approval, a copy of the original contract and any amendments must accompany the proposed amendments. All change orders, amendments to contract and supplemental agreements must be signed by the Purchasing Agent.

RENEWAL OF CONTRACTS
Contracts for services shall not usually cover a period of more than one (1) year, although longer periods may be approved. Unless exempted from competitive bidding procedures, contracts for goods and service should not extend, either by original contract or by extension, beyond five (5) years unless competitive bids/proposals have been sought or approval is obtained from the Purchasing Agent.

Contracts shall not be renewed without thorough consideration of contract performance, availability of new or better contractors, changing circumstances and other factors which could affect the existing contract to determine whether its renewal is the most appropriate and cost effective option.

Any decision to renew a contract must be made prior to the termination date of the existing contract. It is recommended that planning for renewal or a new contract begin not later than sixty (60), nor earlier than one hundred twenty (120) days prior to the existing termination date depending on the complexity of the contract and renewal. Prior to any renewals, department heads or Contract Administrators shall consult with Purchasing.

Renewal shall not be used to circumvent any required bidding processes.

CLOSING OUT OR TERMINATING THE CONTRACT
All contractual relationships must eventually either be closed-out upon completion of all the work or terminated prior to completion. A contract closeout is an administrative procedure involving formal acceptance of all contract deliverables and payment of the contractor’s final invoice. A contract termination is generally a unilateral action that stops work on all or part of the contract for cause or convenience. A contract can also be terminated by mutual agreement in the same way that a contract is amended.

Termination of a contract consists of three steps: (1) close out the contract; (2) issue a Stop Work Order; and (3) settle all claims. Step 1 is performed only upon satisfactory completion of all work. Steps 2 and 3 are performed only to terminate a contract for cause or convenience.

How to Close Out the Contract
A contract should not be closed out until the City is satisfied that all contractual obligations have been met by the contractor. This occurs when two conditions have been met:

  • The required products or services have been delivered and tested/inspected; and
  • The results of these tests and inspections indicate that the required products or services comply with the technical specifications.

Where appropriate, the City shall formally notify the contractor, in writing, of the department’s final acceptance of the work, as soon as these conditions are met. The contractor’s final invoice can now be processed.

How to Issue a Stop Work Order
All or part of the contract may be terminated for cause whenever the contractor refuses or clearly fails to meet contractual performance requirements. Common causes for default include; failure to deliver acceptable products or services; failure to meet scheduled delivery dates or contractual milestones; failure to resolve disputes or offer explanations on disputed terms, conditions or requirements; or demonstrated lack of progress that is harmful to the jurisdiction.

Prior to terminating a contract for cause, consult with Purchasing.

The contractor shall be warned that he/she is in default before work is actually stopped. This warning shall consist of a formal letter from the City specifying how the contractor is in default and suggesting that these problems be corrected within a specified time frame. This warning provides the contractor with an opportunity to correct the problems or dispute the City’s claims before a Stop Work Order is issued. Depending upon the response the City may:

  • Authorize the contractor to proceed under the original or a revised schedule.
  • Allow the contractor to continue if he/she agrees to subcontract specified portions of the work to a reliable outside source.
  • Issue a Stop Work Order.

If a Stop Work order is required, it shall be a formal letter signed by an authorized City representative and reviewed by the City Attorney. The letter shall state:

  • The effective date of the Stop Work Order;
  • The portion of the contract covered by the Stop Work order;
  • Instructions for stopping work and canceling any purchase orders; and
  • A request that the contractor acknowledge receipt of the Stop Work Order.

If the contract provides for termination without cause, notice shall be given as provided by the contract. A formal Stop Work Order is not necessary.

Outstanding Contract Obligations
When a contract is terminated, the contractor may or may not be due any money and the City may or may not be due any monetary damages, materials, equipment or partially complete work. The City should make every effort to determine the status of contract obligations prior to terminating the contract.

VENDOR REQUESTS FOR CHANGES OR CANCELLATIONS

General Policy
When a vendor requests a change or cancellation to a purchase order or contract that will result in additional cost to the city, Purchasing’s policy is to deny the request for a change or cancellation unless such denial will cause documented undue hardship to the vendor or unless there is no reasonable alternative. If the vendor refuses to perform according to the original contract, he will be in breach of contract.

"Price in Effect at Time of Shipment"
In the rare case where Purchasing accepts a "price in effect at time of shipment" offer, the purchase order should so state and the quote or bid file should document the necessity of accepting such an offer.
If the price increases between the date of order and date of shipment, the vendor should supply the buyer with documentation, generally in the form of old and new published price lists.

BREACH OF CONTRACT - DEFINITIONS

Actual Breach
Actual breach of contract is defined as a failure to perform on time and in a manner required by the contract. This includes failure to perform at all, as well as delivering the wrong goods or defective goods.

Anticipatory Breach
Anticipatory breach can be defined as the statement by one party, made prior to the time performance is required under the contract, that it does not intend to perform when performance is due, or the intentional act by one party to disable himself so that he is unable to perform.

In the case of anticipatory breach, the City must have actual evidence of the breach before employing legal remedies.

It is Purchasing’s policy to document the vendor’s statement in writing either by asking for a letter from the vendor stating his position or by issuing a letter to the vendor confirming the vendor’s verbal statement to Purchasing and setting forth a deadline for the vendor’s written reply if Purchasing’s letter is incorrect.

If the City does not cancel the contract, materially change its position (i.e. orders substitute goods) or otherwise indicate that it considers the repudiation final, the vendor may retract its repudiation. Retraction must occur before performance is due.

ENFORCING CONTRACT PROVISIONS

Vendor’s Right to Cure
The vendor has a right to cure improper tender or delivery as follows:

  • Where the City rejects delivery of non-conforming goods and the time for performance has not passed, the vendor may notify the City of its intention to cure and then within the contract time make a conforming delivery.
  • Where the City rejects a non-conforming tender which the vendor has reasonable grounds to believe would be acceptable, he may notify the City of his intent to cure and have further reasonable time to substitute a conforming tender.

Enforcement
The following steps shall be followed when breach of contract has occurred:

  1. 1. Notify the vendor and Purchasing verbally that the vendor has breached the contract and in what way breach has occurred. Reach an understanding with the vendor as to what he/she intends to do. If a vendor intends to remain in default, advise the vendor of the City’s legal rights, the right to obtain comparable goods (known as "cover") elsewhere and charge the company with the difference between the contract price and the "cover" price if the "cover" price is higher. The City may obtain this reimbursement for damages by deducting it from any money due the vendor or by accepting another form of vendor payment.

    Note: Barring a vendor’s substantiated anticipatory breach, the City may not take action to obtain cover until the promised time for performance (delivery date) has passed or the goods have been rightfully rejected.
  2. Document the verbal understanding, including a summary of the City’s legal rights, as appropriate, in writing, and mail to the vendor; send a copy to Purchasing and attach a copy to the Purchasing Document. The letter should set forth a date by which the vendor must reply or cure his default in order to avoid legal action by the City. It should also state that a failure to resolve this problem may result in removal from Purchasing’s bid list. Preparation of this letter must be coordinated with Purchasing and must be approved as to form by the City Attorney prior to mailing to the vendor.
  3. If the vendor fails to fulfill contract requirements and has not replied in writing with an alternate proposal which is acceptable under the circumstances, Purchasing shall issue a written cancellation, signed by Purchasing, and approved by the City Attorney citing the vendor’s breach of contract and shall proceed to obtain comparable goods elsewhere. It is assumed at this point that the City has exhausted all reasonable expectation of obtaining contract performance and cannot wait any longer for the goods.

CONTRACT ADMINISTRATION - FILES
It is imperative from a legal perspective that contract files, especially those pertaining to construction projects are detailed and complete. The following is a list of the types of correspondence and documents that should be kept, as originals or copies depending upon the circumstance. This list is by no means exhaustive and merely reflects those documents that would be critical in the event of litigation or disputes.

  • Copies of All Contracts Pertaining to the Project
    • Architect
    • Construction
    • Consultants
    • Interlocal/Cooperative Agreements
    • Grants
  • Notice of Award Letters
  • Copy of the Purchase Order
  • Requests for Insurance and Bonds
  • Memos/Letters/Reports
    • Field Reports
    • Meeting Notes
    • Correspondence
    • Daily Diaries
    • Orders of Materials
  • Copies of Bonds and Insurance Certificates
  • Change Orders and Changer Order Correspondence
  • Notices of Breach
  • Notice of Completion
Chapter12345678910111213141516
  Home | Policy & Procedures | Vendor Guide | Current Bids
Plan Holder List | Bid Result | Vendor Registration | Survey Page
City of Visalia | Link 1 | Link 2 | Contact US

Site Designed & Developed by LEALGRAFIX